Off-Plan Handover and Snagging in Dubai: A Buyer's Checklist

Updated November 2026

When your Dubai off-plan property is ready, there's a sequence before you get the keys: the handover notice, snagging the unit for defects, the developer's defects liability, the transfer and title deed at the Dubai Land Department, and the final payments. This guide walks through each step and what to check.

Handover terms and defects-liability periods are set by your Sale and Purchase Agreement and UAE law. We state the process and flag what varies by contract — read your SPA and take advice on anything serious.

What handover means

Handover is the point where a completed property passes from the developer to you. For an off-plan purchase, it comes after the developer receives the building completion certificate and notifies you that the unit is ready.

Before you take the keys and make the final payment, you inspect the property — 'snagging' — and complete the transfer at the Dubai Land Department. Treat the handover notice as the start of your final steps, not the finish line.

Before you're called for handover

A few things to have in order before the developer invites you to inspect and complete.

  • Check your payments and Oqood. Off-plan payments go into the project's escrow account, and your purchase is registered on Oqood, the DLD's off-plan register. Make sure your payments and registration are up to date.
  • Read the SPA again. Your Sale and Purchase Agreement sets the unit's specification, the completion date and the handover terms. Re-read it so you know exactly what you were promised.
  • Wait for the completion certificate. The developer can only hand over once the project has its building completion certificate. The handover notice starts the clock on your final payment and inspection.

Snagging: inspecting for defects

Snagging is a careful inspection of the finished unit against the contract and good building standards, listing every defect — a 'snag list' — for the developer to fix before you accept the property. You can snag it yourself or hire a professional snagging company; many buyers do the latter for a brand-new unit.

Inspect before you sign the handover acceptance, because signing can be read as accepting the property's condition. Put the snag list in writing, give the developer the chance to fix the items, and re-inspect once they say it's done.

  • Walls, floors, paint and joinery — for cracks, chips and poor finishing.
  • Doors, windows, locks and cupboards — that they open, close and seal.
  • Air conditioning, plumbing and drainage, sockets, switches and lighting.
  • Kitchen and bathroom fittings, water pressure and any supplied appliances.
  • That the unit matches the SPA — the size, layout and specification you paid for.

The developer's defects liability

Fixing the snag list is not your only protection. Under UAE law a developer carries a defects liability after handover: broadly, around 10 years for major structural defects — the structure, foundations and load-bearing elements — and about one year for the mechanical, electrical and plumbing (MEP) works and finishes. Your SPA should restate the exact periods.

So a defect you find after moving in may still be the developer's to fix. Report defects in writing as soon as you spot them, and consider a second inspection near the end of the first year. For the precise terms, check your SPA, and take legal advice if a serious defect appears.

Transfer, Oqood and the title deed

Once you accept the unit, the sale is transferred at the Dubai Land Department. For a completed off-plan property, the Oqood registration is converted into a title deed in your name after the final payment and the DLD transfer.

The 4% DLD transfer fee and the registration trustee fee are due at this stage if they weren't paid earlier in the purchase, along with any final instalment to the developer. Check what's outstanding with both the developer and the DLD before you sign off.

Getting the keys and moving in

With the transfer done, you receive the keys and access cards. Connect DEWA and the cooling in your name, register with the owners' association, and budget for the service charge, which pays for the building's shared upkeep.

If you plan to let the property out rather than live in it, read our landlord guide; to let it short-term to visitors, you'll need a holiday-home permit first.

Read the whole process in our guide to buying off-plan in the UAE, budget the purchase with the buying cost calculator, and see how off-plan compares with a ready home in off-plan vs ready. Taking the keys to let it out? See the landlord guide.

Frequently asked questions

What is snagging in Dubai?

Snagging is a detailed inspection of a finished property against the contract and good building standards, listing every defect — a 'snag list' — for the developer to fix before you accept handover. You can do it yourself or hire a professional snagging company.

When should I snag an off-plan property?

Before you sign the handover acceptance and make the final payment, because signing can be read as accepting the unit's condition. Give the developer your snag list, let them fix the items, and re-inspect before you take the keys.

How long is a developer liable for defects in Dubai?

Broadly, around 10 years for major structural defects and about one year for the mechanical, electrical and plumbing works and finishes, running from handover. The exact periods are in your Sale and Purchase Agreement — check it, and take legal advice if a serious defect appears.

What happens at off-plan handover in Dubai?

The developer notifies you once the project has its completion certificate, you inspect (snag) the unit, the sale is transferred at the Dubai Land Department, your Oqood registration becomes a title deed after the final payment, and you receive the keys and connect DEWA.

Do I pay the DLD fee at handover?

The 4% Dubai Land Department transfer fee and the registration trustee fee are due when the property is registered in your name, along with any final payment to the developer — unless they were already settled earlier. Confirm what's outstanding with the developer and the DLD before handover.

Sources

Handover and defects-liability terms vary by contract and are set by your SPA and UAE law. This guide is general information, not legal advice; read your SPA and take advice on anything serious.